Skip to main content

Scope

Batt insulation is installed at the attic floor
Batt insulation is installed at the attic floor

Insulate a vented attic in an existing home by installing batt insulation on the ceiling plane of the attic, as follows:

  • Before any retrofit work is done, inspect the roof and attic; repair any leaks, remove active knob and tube wiring, and remediate any hazardous materials.
  • If existing bath fans vent into the attic, they must be vented to the outside.
  • Remove any existing insulation, debris and dust, and prepare the attic floor for air sealing and fibrous batt insulation.
  • Seal all attic floor penetrations with sealant, one-part spray foam, or rigid blocking material as needed.
  • Verify that proper ventilation of the attic is provided with soffit vents (preferred) or gable and ridge vents. Verify that there is a baffle at each soffit vent extending from the top plate to above the height of the insulation to provide a pathway for ventilation air while keeping insulation out of the soffit vents.
  • Install batt insulation over the attic floor to levels that meet or exceed the current adopted building and energy codes.

This approach is suitable for projects with a vented attic where the thermal boundary is established at the attic floor/ceiling plane. This approach requires that there be sufficient height between the underside of the roof deck and the top plate at the eave to install the full code-required amount of insulation while maintaining an air gap for ventilation above the insulation. Installing HVAC ducts and air handlers in vented attics is not recommended.

See the following Building America Solution Center guides for more information:

See the U.S. Department of Energy’s Standard Work Specifications (SWS) for more guidance on installing batt insulation and batt insulation over existing insulation.

See the Compliance Tab for links to related codes and standards and voluntary federal energy-efficiency program requirements.

Description

Many older homes have little or no attic insulation. Batt insulation can be installed at the ceiling plane/attic floor to improve thermal performance in a vented attic.

When attic batt insulation is installed in two layers (Figure 1), the first layer of batts is typically installed between and parallel to the ceiling joists and the second layer is typically run perpendicular to the first layer, to cover the tops of the joists, thus stopping thermal bridging through the joists. The second layer could also be installed parallel to the first layer of batts but with the batts offset so that the seams don’t line up. The batts should be split to fit snugly around any wiring or pipes. The batts should be installed in accordance with RESNET Grade 1 installation criteria (See BASC guide: Insulation Installation Achieves RESNET Grade I as well as Insulation Installation [RESNET Grade 1] - Part 1 and Insulation Installation [RESNET Grade 1] - Part 2).

The ceiling plane or attic floor should be thoroughly air sealed prior to installing insulation. Robust and continuous air control is critical to a high-performance thermal enclosure. The existing insulation must be removed to provide access to the ceiling plane for air sealing. Debris and dust should also be removed so that sealants will have good adhesion. Seal all cracks, seams and holes using caulk or spray foam sealants. Use solid blocking for any larger holes or open soffits. Metal blocking and collars can be constructed around hot flues to keep insulation from touching them. Covers can be purchased or constructed to cover, air seal, and insulate recessed can lights that are not insulated ceiling airtight (ICAT) rated. (See Attic Air Sealing Guide and Details.)

If existing insulation was removed from the attic floor to perform air sealing, it may be reinstalled if it is in good condition.  However, existing attic insulation is often contaminated with construction debris, plaster scraps, animal droppings, etc. Older loose-fill may be vermiculite insulation which can contain asbestos. The safest approach may be to dispose of the old insulation and install only new insulation.

Guidance for mitigating asbestos-related issues from HUD, EPA, NIH, OSHA and FEMA is available in Homeowner's and Renter's Guide to Asbestos Cleanup After Disasters and Asbestos: Worker and Employer Guide to Hazards and Recommended Controls

The presence of flooring above the ceiling joists in an attic will make it difficult to air seal at the ceiling plane (attic floor).  If the air control is to be established at the ceiling plane, then any attic flooring installed above that must be removed to provide full access to the ceiling surface.  Alternately, it may be possible to transition the air barrier to the top of the existing attic floor. To successfully execute this option, sufficient insulation is required outboard (on top of) the floor to control condensation and a robust air control connection must be made from the top of the exterior walls to the perimeter of the attic flooring.

In climate zones 6 or higher, a Class I vapor barrier (e.g., polyethylene) or Class II vapor retarder should be installed above the ceiling drywall as required by code. Class I vapor barriers should be avoided in climate zones 5 and below, as condensation can occur on the attic side of the vapor barrier in summer months during air conditioning periods. (See BSD 102 Attic Ventilation.)

One benefit of a vented (rather than unvented) attic is that interior-sourced moisture will be vented out of the attic space before causing damage to the roof sheathing. Another advantage of vented attics in cold climates is that they help to reduce the chances of ice damming on the roof. Ice dams occur when heat leaks from the conditioned space (through holes in the ceiling plane, insufficient insulation, or heat loss from ductwork) and melts the snow on the roof. This melted snow travels down to the edges of the roof where it refreezes, creating icicles and ice dams. Attic ventilation helps to “flush away” this heat before it can melt the snow. (See BSI-046: Dam Ice Dam, and BSD-135: Ice Dams.)   

The vented attic approach requires that there be sufficient height at the attic eaves for code-level required amounts of insulation. In mixed- and cold climates (zones 4 and above), inadequate insulation raises risks of wintertime condensation at the top plate due to cold surfaces. If the roof is too low at the eaves to install adequate amounts of batt insulation, then alternative solutions are to fill the space over the top plate to the baffle with closed-cell spray foam or to cover the top plate area with rigid foam board. (Spray foam and rigid foam have higher R-values per inch than blown insulation. Spray foam has the added advantage of air sealing the top plate-to-drywall seams and the baffle-to-top plate seam.) Another option is to convert the attic to a sealed, insulated space by sealing the soffit vents and insulating along the underside of the ceiling deck with closed-cell spray foam or above the roof deck with rigid foam. In new home construction, a common solution to increase the roof height for insulation above the top plate is to use raised heel trusses. Older existing roofs are unlikely to have raised heel trusses and raised heel trusses are not likely to be installed as a retrofit measure unless a complete reconstruction of the roof is required, for example if a second or third story is being added.

The vented attic approach requires that there be sufficient height at the attic eaves to maintain an air gap above the insulation for ventilation air traveling from the soffit vents to the ridge vents. The vent space should be at least 2 inches high and the width of the framing bay at each soffit vent (Lstiburek 2006). Baffles should be installed at each soffit vent to provide this pathway for ventilation air to move up past the insulation along the underside of the roof deck to ridge vents or mushroom cap vents located near the ridge. The lower edge of the baffle can be sealed to the attic floor at the outside edge of the top plate with spray foam, which also air seals the top plate-to-dry wall seams. The baffles also serve to prevent insulation from covering the soffit vents and they can prevent “wind washing,” i.e., when wind blows in the soffit vents and pushes the insulation back from the eaves.

If the attic does not have soffit vents, attic ventilation can be provided by installing other types of vents such as gable or eyebrow vents down low near the attic floor, along with ridge vents or mushroom cap vents located up near the roof ridge.

Powered attic ventilators (thermostatically controlled fans that exhaust attic air during hot weather) can result in increased infiltration (and associated higher cooling loads).  Studies have shown that powered ventilators have higher electricity consumption than their associated air conditioner savings (FSEC 2005/ Literature Review of the Impact and Need for Attic Ventilation in Florida Homes).

Installing HVAC ducts and air handlers in vented attics is not recommended. Locating ductwork and/or air handling equipment in a vented attic can contribute to energy losses, performance issues, and ice dam formation in snowy climates, especially if the ducts and air handlers are leaky or poorly insulated.  One exception is if the ductwork can be encapsulated in spray foam and buried beneath the attic floor batt insulation. The ducts must be tightly air sealed and covered with a sufficient amount of spray foam insulation to minimize the risk of condensation forming on the outside of the ducts. See Ducts Buried in Attic Insulation.  However, because mechanical equipment such as air handlers cannot be adequately air sealed, locating them in a vented attic is not recommended. If the air handler must be located in the attic then consider converting the attic to a sealed, insulated space.

Batt insulation is installed at the attic floor
Batt insulation is installed at the attic floor
Batt insulation is installed at the attic floor
Source
Courtesy Of
BSC
Figure 1. Batt insulation is installed at the attic floor (Source: Courtesy of Building Science Corporation).

How to Insulate Attic Floor with Batt Insulation

  1. Before any retrofit work is done, inspect the work area for active knob and tube wiring, bathroom fans venting into attics, roof leaks, and other hazardous conditions. Repair these conditions prior to adding insulation. Inspect for and remove or remediate hazardous materials like asbestos-containing vermiculite insulation.
  2. Remove any existing insulation, debris, and dust from the floor of the attic, and clean the work area to allow for adequate adhesion of sealants.
Clean the attic floor of debris prior to installing new attic insulation. Use baffles to provide a path for ventilation air entering the attic from the soffit vents
Clean the attic floor of debris prior to installing new attic insulation. Use baffles to provide a path for ventilation air entering the attic from the soffit vents
Clean the attic floor of debris prior to installing new attic insulation. Use baffles to provide a path for ventilation air entering the attic from the soffit vents
Source
Author(s)
Lstiburek Joseph W
Organization(s)
Building Science Corporation,
BSC
Description

Document providing background and approach for the prep work necessary prior to adding attic insulation - focusing on combustion safety, ventilation for indoor air quality, and attic ventilation for durability.

Figure 2. Clean the attic floor of debris prior to installing new attic insulation. Use baffles to provide a path for ventilation air entering the attic from the soffit vents (Source: Attic Air Sealing Guide and Details, GM-1001 2010). 

   3. Seal all ceiling joints and penetrations with sealant. Seal top plate-to-drywall seams and top plate-to-baffle seams. Provide additional solid blocking for large holes and open soffits, install metal blocking        and collars around hot flues, and install covers over non-ICAT-rated recessed can lights.  (See BSC. 2013. Attic Air Sealing Guide and Details).  Don’t block intentional openings such as combustion air      
       ducts and soffit, ridge, and gable vents.

Seal the drywall to top-plate seams and the lower edge of baffles to the top plate to prevent the air coming from soffit vents from flowing under baffles into insulation.
Seal the drywall to top-plate seams and the lower edge of baffles to the top plate to prevent the air coming from soffit vents from flowing under baffles into insulation.
Seal the drywall to top-plate seams and the lower edge of baffles to the top plate to prevent the air coming from soffit vents from flowing under baffles into insulation.
Source
Author(s)
Lstiburek Joseph W
Organization(s)
Building Science Corporation,
BSC
Description

Document providing background and approach for the prep work necessary prior to adding attic insulation - focusing on combustion safety, ventilation for indoor air quality, and attic ventilation for durability.

Figure 3. Seal drywall to top-plate seams. Seal lower edge of baffle to top plate to prevent incoming air from soffit vents from flowing under baffles into insulation (Source: Attic Air Sealing Guide and Details, GM-1001 2010). 
Seal all drywall-to-top plate seams and penetrations at the attic floor
Seal all drywall-to-top plate seams and penetrations at the attic floor
Seal all drywall-to-top plate seams and penetrations at the attic floor
Source
Author(s)
Lstiburek Joseph W
Organization(s)
Building Science Corporation,
BSC
Description

Document providing background and approach for the prep work necessary prior to adding attic insulation - focusing on combustion safety, ventilation for indoor air quality, and attic ventilation for durability.

Figure 4. Seal all drywall-to-top plate seams and penetrations at the attic floor (Source: Attic Air Sealing Guide and Details, GM-1001 2010). 

    4. Verify that proper ventilation of the attic is provided with soffit and ridge vents or eyebrow, gable end, mushroom cap, and/or other vents. (See Figure 5.) If soffit vents exist, inspect existing baffles and      install new baffles if needed. (See Figure 3.)

  1. Attic ventilation approaches.
    Figure 5. Attic ventilation approaches (Source: Courtesy of Building Science Corporation). 
  2. Install batt insulation over the attic floor to levels that meet or exceed the current adopted building and energy codes for thermal performance.  When applicable, install the insulation in two layers in perpendicular directions (or alternately, with offset seams), with the second layer over the ceiling joists, to control thermal bridging.  Cover the entire ceiling ensuring that the batts cover the exterior wall top plates and are in contact with the baffles to provide adequate thermal resistance at the eaves.
     
Batt insulation is installed in two layers in perpendicular directions against the baffle to full required insulation height
Batt insulation is installed in two layers in perpendicular directions against the baffle to full required insulation height
Batt insulation is installed in two layers in perpendicular directions against the baffle to full required insulation height
Source
Author(s)
Lstiburek Joseph W
Organization(s)
Building Science Corporation,
BSC
Description

Document providing background and approach for the prep work necessary prior to adding attic insulation - focusing on combustion safety, ventilation for indoor air quality, and attic ventilation for durability.

Figure 6. Batt insulation is installed in two layers in perpendicular directions against the baffle to full required insulation height (Source: Attic Air Sealing Guide and Details, GM-1001 2010). 
Batt insulation is installed in two layers with offset seams against the baffle to full code-required insulation height
Batt insulation is installed in two layers with offset seams against the baffle to full code-required insulation height
Batt insulation is installed in two layers with offset seams against the baffle to full code-required insulation height
Source
Author(s)
Lstiburek Joseph W
Organization(s)
Building Science Corporation,
BSC
Description

Document providing background and approach for the prep work necessary prior to adding attic insulation - focusing on combustion safety, ventilation for indoor air quality, and attic ventilation for durability.

Figure 7. Batt insulation is installed in two layers with offset seams against the baffle to full code-required insulation height (Source: Attic Air Sealing Guide and Details, GM-1001 2010). 

Ensuring Success

Remediate any hazardous conditions that will be affected (e.g., exposed or aggravated) by the planned work. Examples of hazardous materials that may be found in attic/roof assemblies of existing structures include (but are not limited to) lead, asbestos, mold, animal dropping/remains, etc. Follow applicable laws and industry procedures for mitigation of hazardous materials. Engage the services of a qualified professional when needed.

For more information on vermiculite, see the EPA guide: Protect Your Family from Asbestos – Contaminated Vermiculite Insulation.

For guidance on handling knob and tube wiring, see Weatherization Assistance Program guide: Retrofitting Insulation in Cavities with Knob-and-Tube Wiring an Investigation into Codes, Safety, and Current Practices.

Seal all penetrations to provide a continuous air control layer at the attic floor. Visual inspection, infrared thermography, and blower door testing are all tools that can be used to verify air barrier continuity.

Install batt insulation to provide adequate thermal resistance and to the levels specified in the current adopted building and energy codes.

Electrical junction boxes accessible from the attic will be buried during this insulation retrofit.  The NEC (Article 314.29, 2005 NEC) requires junction boxes to be accessible "without removing any part of the building."  This clause could be interpreted as including or excluding attic insulation.  The ideal approach would elevate the junction box above the insulation level; alternately, a flag marker could be placed to indicate junction box location.  A local code official could provide further guidance.

All vented roofs must have an adequate amount of venting according to the applicable current adopted building code.  If the roof is not vented according to the applicable building code then a qualified contractor in the state should be engaged to install the necessary venting.

Region

The ceiling/attic floor assembly should be designed for a specific hygrothermal region, rain exposure zone, and interior climate.  The climate zones are shown on the map below, which is taken from Figure C301.1 of the 2012 IECC. 

The map in Figure 1 shows the climate zones for states that have adopted energy codes equivalent to the International Energy Conservation Code (IECC) 2009, 12, 15, and 18. The map in Figure 2 shows the climate zones for states that have adopted energy codes equivalent to the IECC 2021. Climate zone-specific requirements specified in the IECC are shown in the Compliance Tab of this guide. 
 

IECC climate zone map
IECC climate zone map
IECC climate zone map
Source
Author(s)
International Code Council
Organization(s)
ICC
Description

2012 edition of code establishing a baseline for energy efficiency by setting performance standards for the building envelope (defined as the boundary that separates heated/cooled air from unconditioned, outside air), mechanical systems, lighting systems and service water heating systems in homes and commercial businesses.

Figure 1. Climate Zone Map from IECC 2009, 12, 15, and 18 (Source: 2012 IECC).
Climate Zone Map from IECC 2021
Climate Zone Map from IECC 2021
Climate Zone Map from IECC 2021
Source
Author(s)
International Code Council
Organization(s)
ICC
Description

2021 edition of code establishing a baseline for energy efficiency by setting performance standards for the building envelope (defined as the boundary that separates heated/cooled air from unconditioned, outside air), mechanical systems, lighting systems and service water heating systems in homes and commercial businesses.

Figure 2. Climate Zone Map from IECC 2021 (Source: 2021 IECC).

The insulation levels should be based on the minimum requirements for vapor control in the current adopted building code and the minimum requirements for thermal control in the current energy code. The table below provides the minimum thermal resistance (R-value) requirements specified in the 2009 IECC (ICC 2009b) and the 2012 IECC (ICC 2012b) based on climate zone for ceiling/attic floor assemblies.

Attic Insulation Requirements per the 2009 and 2012 IECC.

Table 1. Attic Insulation Requirements per the 2009 and 2012 IECC.

 

Training

Right and Wrong Images

Wrong - Batt insulation does not provide complete coverage across the attic floor so ceiling joists are exposed resulting in thermal bridging.
Wrong - Batt insulation does not provide complete coverage across the attic floor so ceiling joists are exposed resulting in thermal bridging.
Wrong - Batt insulation does not provide complete coverage across the attic floor so ceiling joists are exposed resulting in thermal bridging.
Source
Courtesy Of
BSC
Right – Batt insulation provides additional insulation for the home’s main duct chase.
Right – Batt insulation provides additional insulation for the home’s main duct chase.
Right – Batt insulation provides additional insulation for the home’s main duct chase.
Source
Wrong - Batt insulation is poorly installed leaving gaps along the ceiling.
Wrong - Batt insulation is poorly installed leaving gaps along the ceiling.
Wrong - Batt insulation is poorly installed leaving gaps along the ceiling.
Source

Videos

More Info

Case Studies

References and Resources

Publication Date
·
Author(s)
ENERGY STAR
·
Organization(s)
U.S. Environmental Protection Agency,
EPA,
ENERGY STAR
Description
Guide for homeowners describing how to find and seal basement and attic air leaks, determine if attic insulation is adequate, make improvements safely, and reduce energy bills.
Publication Date
·
Author(s)
Lstiburek Joseph W
·
Organization(s)
Building Science Corporation,
BSC
Description
Document providing background and approach for the prep work necessary prior to adding attic insulation - focusing on combustion safety, ventilation for indoor air quality, and attic ventilation for durability.
Publication Date
·
Author(s)
Lstiburek Joseph W
·
Organization(s)
Building Science Corporation,
BSC
Description
Article describing strategies for reducing the risk of ice dam formation on roofs in winter.
Publication Date
·
Author(s)
Straube John
·
Organization(s)
Building Science Corporation,
BSC
Description
Article outlining the casuses and solutions for ice dam problems.
Publication Date
·
Author(s)
Neuhauser Ken,
Gates Cathy,
Pettit Betsy
·
Organization(s)
Building Science Corporation,
BSC
Description
Guidebook providing useful examples of high performance retrofit techniques for the building enclosure of wood frame residential construction in a cold and somewhat wet climate.
Publication Date
·
Author(s)
Lstiburek Joseph W
·
Organization(s)
Building Science Corporation,
BSC
Description
BSD-102 report providing guidance about whether to construct a vented or unvented attic based on hygro-thermal zone.

*For non-dated media, such as websites, the date listed is the date accessed.

Contributors to this Guide

The following authors and organizations contributed to the content in this Guide.

Building Science Corporation, lead for the Building Science Consortium (BSC), a DOE Building America Research Team

Sales

Building Science-to-Sales Translator

High-R Attic Insulation = High-Efficiency or Ultra-Efficient Attic Insulation

Image(s)

Technical Description

There are two levels of attic insulation: high-efficiency insulation, which meets the 2015 International Energy Conservation Code, and ultra-efficient insulation, which is 25% more efficient than this national code. Using high-efficiency and ultra-efficient insulation along with professional installation (e.g., no gaps, voids, compression, or misalignment with air barriers;  complete air barriers; and minimal thermal bridging) creates conditioned spaces that require very little heating  and cooling, along with even comfort and quiet throughout the house.

High-Efficiency or Ultra-Efficient Attic Insulation
Sales Message

High-efficiency attic insulation helps provide added thermal protection. What this means to you is less wasted energy along with enhanced comfort and quiet. Knowing there is one opportunity to optimize performance during construction, wouldn’t you agree it’s a great opportunity to meet or exceed future codes?

Last Updated

Questions? Comments? Contact our webmaster.

Disclaimer

This content is a work created with funding provided by the United States Department of Energy under Contract no DE-AC05-076RL01830 for the operation of Pacific Northwest National Laboratory. The information and guidance provided by Pacific Northwest National Laboratory (PNNL) in the content are intended solely for educational purposes only and do not constitute formal training or certification. It is provided with the explicit understanding that neither the United States Government nor the United States Department of Energy, nor the Contractor, nor any or their employees, nor any jurisdiction or organization that has cooperated in the development of these materials, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness or any information, apparatus, product, software, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof, or Battelle Memorial Institute. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof. Viewers assumes full responsibility for all actions that they may take from information provided in this content including ensuring the safety, code compliance, and proper functionality of any products they choose to install. Installation and use of such products should be performed in accordance with local regulations and manufacturer instructions.