Skip to main content

Skylight Shaft Walls

    Scope
    Scope Images
    Image
    Install insulation and an air barrier around skylight shafts.
    Scope

    Install insulation and an air barrier around skylight shafts.

    • If non-rigid insulation is used in the wall cavities of the skylight shaft, install a rigid air barrier on the exterior side of the shaft wall framing to prevent the cavity insulation from sagging and to create a continuous thermal barrier.
    • Seal all seams, gaps, and holes in the air barrier with caulk or foam. Rigid air barrier material could include rigid foam insulation, drywall, plywood, or OSB, among others.
    • If spray foam insulation is used for the wall cavity insulation, the spray foam can serve as the air barrier if it is at least 5.5 inches thick if open-cell or at least 1.5 inches thick if closed-cell spray foam insulation.  
    • Ensure that the air barrier is continuous and in full contact with the insulation.
    • ENERGY STAR requires that an air barrier be installed at the exterior vertical surface of the wall insulation in all climate zones and also that an air barrier be installed at the interior vertical surface in IECC Climate Zones 4-8 (ENERGY STAR).

    See the Compliance Tab for related codes and standards requirements, and criteria to meet national programs such as DOE’s Zero Energy Ready Home program, ENERGY STAR Single-Family New Homes, and EPA Indoor airPLUS.

    Description
    Description

    When skylights are installed, special attention must be paid to insulating the vertical shafts extending from the roof to the ceiling. Unsealed attics are often insulated along the attic floor with blown fiberglass or cellulose insulation. A different type of insulation will need to be installed along the skylight shaft walls, one that will maintain full alignment (or contact) with the back side of the sheathing for the height of the skylight shaft walls and that will maintain at least the minimum required depth of insulation along the full height. Skylight shaft walls should be insulated to the same R-value as other exterior walls if the attic they pass through is not insulated.

    There are several options for insulating skylight shafts. One option to consider, especially if several skylights are being installed, is to make the attic part of the conditioned space of the home by installing insulation at the roof deck, either by spray foaming along the underside of the roof deck or installing rigid foam above the roof deck, or by constructing the roof with structural insulated panels (SIPs). This insulated attic would also provide a conditioned space for any HVAC equipment installed in the attic.

    If the skylight shafts are installed in a vented, uninsulated attic, then the sides of the skylight shaft should be insulated. This can be accomplished using spray foam or rigid foam, or by constructing the shaft walls with SIPs. Fiberglass batt insulation is not recommended for insulating the skylight shaft walls because it can settle or pull away from the wall. If batt insulation is used, it should be covered with a rigid material such as rigid foam, which will provide an interior air barrier and ensure that the batts will not slide down or fall away from the wall. These materials may be installed by insulators, framers, or subcontractors or vendors hired specifically to install the skylight. This task should be included in the contract for the appropriate trade depending on the workflow at the specific job site.

    How to Insulate a Skylight Shaft

    1. Select the skylight size and location to avoid cutting roof or ceiling rafters, if possible. (House designs that use 24-in on-center fully aligned framing members are less likely to require cutting of studs for skylight installation.) Follow the manufacturer’s instructions to install the skylight on the roof deck, properly flashing and integrating the skylight frame with roofing materials to minimize the risk of water intrusion. The roof opening is framed with headers, with framing lumber run horizontally across the opening and securely nailed to the rafters to support the structure.
    2. Install headers across the ceiling opening as you did for the roof opening, using a single header at each end if no ceiling joists are cut or double headers if a ceiling joist has to be cut. If the light shaft will be flared, cut the joist at the angle of the flare.
    3. Cut 2x4 studs (or 2x6 to allow for more cavity insulation) for the corners of the light shaft, angled on each end to fit flush against the rafters and ceiling joists. Next, place studs 24-inch on-center around the opening. Nail 2x2 cleats to the inside edges of the corner studs or use drywall clips to serve as backing for the drywall.

    Or, frame the shaft with structural insulated panels (SIPs) following the manufacturer’s instructions for air sealing the corners, seams, and top and bottom edges.

    1. Fill the stud cavities with spray foam, batt insulation, or rigid foam (Figures 1 and 2). Next, cover them with a layer of rigid foam to achieve the R-value level required for your climate zone.

    Or, nail rigid foam in place over the studs and fill the cavities with blown cellulose or blown fiberglass.

    1. Caulk drywall and rigid foam to framing at all edges. Seal any seams in the rigid foam with caulk, tape, or foam.
    2. Paint drywall with latex paint to serve as the vapor barrier.
    Frame, insulate, and air seal the walls of the skylight shaft as you would an exterior wall.
    Figure 1. Frame, insulate, and air seal the walls of the skylight shaft as you would an exterior wall.

     

    Non-rigid cavity insulation should be covered with a rigid air barrier that is sealed at the edges.
    Figure 2. Non-rigid cavity insulation should be covered with a rigid air barrier that is sealed at the edges.

     

    How to Insulate a Solar Tube

    1. Install the tube according to the manufacturer’s instructions.
    2. Insulate the solar tube with plastic-covered flex duct insulation.
    3. Or - Wrap the tube with unfaced fiberglass batt insulation. Secure the insulation in place with ties. Cover the unfaced batt insulation with flexible foil-faced insulation and secure it with ties and metal tape.
    4. Use spray foam or caulk to air seal the solar tube to the ceiling from above.
    5. Caulk under the decorative ring on the room side of the ceiling.

    For more on installing solar tubes, see the guide Light Tubes.

    Success
    Ensuring Success

    An infrared camera can be used to detect heat loss around the skylight. The insulation installation should be visually inspected by the site supervisor.

    Climate
    Climate

    The map in Figure 1 shows the climate zones for states that have adopted energy codes equivalent to the International Energy Conservation Code (IECC) 2009, 12, 15, and 18. The map in Figure 2 shows the climate zones for states that have adopted energy codes equivalent to the IECC 2021. Climate zone-specific requirements specified in the IECC are shown in the Compliance Tab of this guide. 

    Figure 1. Climate Zone Map from IECC 2009, 12, 15, and 18.
    Figure 1. Climate Zone Map from IECC 2009, 12, 15, and 18. (Source: 2012 IECC)

     

    Climate Zone Map from IECC 2021.
    Figure 2. Climate Zone Map from IECC 2021. (Source: 2021 IECC)

     

    Training
    Right and Wrong Images
    Image
    Wrong – Rigid air barrier not installed to hold insulation in place
    Wrong – Rigid air barrier not installed to hold insulation in place
    Image
    Right – Rigid air barrier is installed to hold insulation in place
    Right – Rigid air barrier is installed to hold insulation in place
    Image
    Wrong – Rigid air barrier not properly sealed around skylight shaft
    Wrong – Rigid air barrier not properly sealed around skylight shaft
    Image
    Right – Rigid air barrier properly sealed around skylight shaft
    Right – Rigid air barrier properly sealed around skylight shaft
    Image
    Wrong – Insulation is misaligned with air barrier
    Wrong – Insulation is misaligned with air barrier
    Videos
    CAD
    CAD Files
    Air sealing at skylight shaft
    Air sealing at skylight shaft
    Download: DWG PDF
    Compliance

    Compliance

    The Compliance tab contains both program and code information. Code language is excerpted and summarized below. For exact code language, refer to the applicable code, which may require purchase from the publisher. While we continually update our database, links may have changed since posting. Please contact our webmaster if you find broken links.

     

    ENERGY STAR Single-Family New Homes, Version 3/3.1 (Rev. 11)

    Rater Field Checklist

    Thermal Enclosure System.
    2. Fully-Aligned Air Barriers.7 At each insulated location below, a complete air barrier is provided that is fully aligned as follows:
    Walls: At exterior vertical surface of wall insulation in all climate zones; also at interior vertical surface of wall insulation in Climate Zones 4-8.9
    2.3 Attic knee walls and skylight shaft walls.10

    Footnote 7) For purposes of this Checklist, an air barrier is defined as any durable solid material that blocks air flow between conditioned space and unconditioned space, including necessary sealing to block excessive air flow at edges and seams and adequate support to resist positive and negative pressures without displacement or damage. EPA recommends, but does not require, rigid air barriers. Open-cell or closed-cell foam shall have a finished thickness ≥ 5.5 in. or 1.5 in., respectively, to qualify as an air barrier unless the manufacturer indicates otherwise. If flexible air barriers such as house wrap are used, they shall be fully sealed at all seams and edges and supported using fasteners with caps or heads ≥ 1 in. diameter unless otherwise indicated by the manufacturer. Flexible air barriers shall not be made of kraft paper, paper-based products, or other materials that are easily torn. If polyethylene is used, its thickness shall be ≥ 6 mil.

    Footnote 9) All insulated vertical surfaces are considered walls (e.g., above and below grade exterior walls, knee walls) and must meet the air barrier requirements for walls. The following exceptions apply: air barriers recommended, but not required, in adiabatic walls in multifamily dwellings; and, in Climate Zones 4 through 8, an air barrier at the interior vertical surface of insulation is recommended but not required in basement walls or crawlspace walls. For the purpose of these exceptions, a basement or crawlspace is a space for which ≥ 40% of the total gross wall area is below-grade.

    Footnote 10) Exterior air barriers are not required for attic knee walls that are ≤ 24 in. in height if an interior air barrier is provided and insulation extends in all directions from the top of this interior air barrier into unconditioned space at the following levels: CZ 1-5: ≥ R-21; CZ 6-8: ≥ R-30.

    Please see the ENERGY STAR Single-Family New Homes Implementation Timeline for the program version and revision currently applicable in your state.

     

    DOE Zero Energy Ready Home (Revision 07)

    Exhibit 1 Mandatory Requirements.
    Exhibit 1, Item 1) Certified under the ENERGY STAR Qualified Homes Program or the ENERGY STAR Multifamily New Construction Program.
    Exhibit 2, Item 2) Ceiling, wall, floor, and slab insulation shall meet or exceed 2015 IECC levels and achieve Grade 1 installation, per RESNET standards.

    Exhibit 2 DOE Zero Energy Ready Home Target Home.
    The U.S. Department of Energy’s Zero Energy Ready Home program allows builders to choose a prescriptive or performance path. The DOE Zero Energy Ready Home prescriptive path requires builders to meet or exceed the minimum HVAC efficiencies listed in Exhibit 2 of the National Program Requirements (Rev 07), as shown below. The DOE Zero Energy Ready Home performance path allows builders to select a custom combination of measures for each home that is equivalent in performance to the minimum HERS index of a modeled target home that meets the requirements of Exhibit 2 as well as the mandatory requirements of Zero Energy Ready Home Exhibit 1.

    Exhibit 2, Insulation and Infiltration) Whole house leakage must be tested and meet the following infiltration limits:

    • Zones 1-2: ≤ 3 ACH50;
    • Zones 3-4: ≤ 2.5 ACH50;
    • Zones 5-7: ≤ 2 ACH50;
    • Zone 8: ≤ 1.5 ACH50;
    • Attached dwellings: ≤ 3 ACH50.

    Footnote 23) Envelope leakage shall be determined by an approved verifier using a RESNET-approved testing protocol

     

    2009-2021 IECC and IRC Window U-Factor Requirements Table

    The maximum U-Factor and Solar Heat Gain Coefficient (SHGC) requirements for fenestration (windows) and skylights in new homes, as listed in the 2009, 2012, 2015, 2018, and 2021 IECC and IRC, can be found in this table.

     

    2009 International Energy Conservation Code (IECC)

    Section 402.4.1 Building thermal envelope - Joints (including rim joist junctions), attic access openings, penetrations, and all other such openings in the building envelope that are sources of air leakage are sealed with caulk, gasketed, weatherstripped or otherwise sealed with an air barrier material, suitable film or solid material. Table 402.4.2 Air Barrier and Insulation Inspection Component Criteria, Air barrier and thermal barrier: Exterior wall insulation is installed in substantial contact and continuous alignment with the air barrier. Air permeable insulation is not used as a sealing material.

    2012 IECC

    Table R402.4.1.1 Air Barrier and Insulation Installation, Air barrier and thermal barrier: A continuous air barrier is installed in the building envelope including rim joists and exposed edges of insulation. Breaks or joints in the air barrier are sealed. Air permeable insulation is not used as a sealing material.

    20152018, and 2021 IECC

    Table R402.1.2 Insulation and Fenestration Requirements – meet or exceed the insulation levels listed in this table.

    Table R402.4.1.1 Air Barrier and Insulation Installation, Walls: Insulation in exterior framed walls is in substantial contact and continuous alignment with the air barrier. Windows, Skylights, and Doors: the space between skylights and framing must be sealed. General requirements: A continuous air barrier is installed in the building envelope; breaks and joints in the air barrier are sealed. Air-permeable insulation is not used as an air-sealing material.

    Section R402.4.1.2 Testing.  The building should be tested for air leakage in accordance with ASTM E 779 or E 1827 (or RESNET/ICC 380 in 2018 IECC) and should have an air leakage rate of ≤ 5 in CZ 1 and 2 or ≤ 3 in CZ 3-8.

    Retrofit:  2009, 2012, 2015, 2018,  and 2021 IECC

    Section R101.4.3 (in 2009 and 2012). Additions, alterations, renovations, or repairs shall conform to the provisions of this code, without requiring the unaltered portions of the existing building to comply with this code. (See code for additional requirements and exceptions.)

    Chapter 5 (in 2015, 2018, 2021). The provisions of this chapter shall control the alteration, repair, addition, and change of occupancy of existing buildings and structures.

     

    2009 International Residential Code (IRC)

    Section N1102.4.1 Building thermal envelope - Joints (including rim joist junctions), attic access openings, penetrations, and all other such openings in the building envelope that are sources of air leakage are sealed with caulk, gasketed, weatherstripped or otherwise sealed with an air barrier material, suitable film or solid material. Table N1102.4.2 Air Barrier and Insulation Inspection Component Criteria, Air barrier and thermal barrier: Exterior wall insulation is installed in substantial contact and continuous alignment with the air barrier. Air permeable insulation is not used as a sealing material.

    2012 IRC

    Table N1102.4.1.1 Air Barrier and Insulation Installation, Air barrier and thermal barrier: A continuous air barrier is installed in the building envelope including rim joists and exposed edges of insulation. Breaks or joints in the air barrier are sealed. Air permeable insulation is not used as a sealing material.

    20152018, and 2021 IRC

    N1102.4.1.1 Air Barrier and Insulation Installation, Walls: Insulation in exterior framed walls is in substantial contact and continuous alignment with the air barrier. Windows, Skylights, and Doors: the space between skylights and framing must be sealed. General requirements: A continuous air barrier is installed in the building envelope; breaks and joints in the air barrier are sealed. Air-permeable insulation is not used as an air-sealing material.

    Retrofit:  2009, 2012, 2015, 2018,  and 2021 IRC

    Section R102.7.1 Additions, alterations, or repairs. Additions, alterations, renovations, or repairs shall conform to the provisions of this code, without requiring the unaltered portions of the existing building to comply with the requirements of this code, unless otherwise stated. (See code for additional requirements and exceptions.)

    Appendix J regulates the repair, renovation, alteration, and reconstruction of existing buildings and is intended to encourage their continued safe use.

     

    American Society for Testing Materials (ASTM) E1677-11

    Standard Specification for Air Barrier (AB) Material or System for Low-Rise Framed Building Walls. This specification covers minimum performances and specification criteria for an air barrier material or system for framed, opaque walls of low-rise buildings. The provisions are intended to allow the user to design the wall performance criteria and increase air barrier specifications for a particular climate location, function, or design.

     

    Air Barrier Association of America (ABAA) 07261

    Self-Adhered Sheet Air Barrier. 2006. Air Barrier Association of America, Walpole, MA. This specification for self-adhered sheet air barriers is developed by a professional association, the Air Barrier Association of America, to provide guidance to the design professional.

    ABAA 07262

    Fluid-Applied Air and Vapor Barrier. 2012. Air Barrier Association of America, Walpole, MA. This specification for air barriers that are fluid-applied and also act as vapor barriers is developed by a professional association, the Air Barrier Association of America, to provide guidance to the design professional.

    ABAA 07263

    Closed Cell, Medium-Density Spray Polyurethane Foam Air Barrier. 2011. Air Barrier Association of America, Walpole, MA. This specification for closed cell, medium-density spray polyurethane foam air barriers is developed by a professional association, the Air Barrier Association of America, to provide guidance to the design professional.

    ABAA 07265

    Fluid-Applied Vapor Permeable Air Barrier. 2012. Air Barrier Association of America, Walpole, MA. This specification for fluid-applied vapor permeable air barriers is developed by a professional association, the Air Barrier Association of America, to provide guidance to the design professional.

    Retrofit
    Existing Homes

    SCOPE

    Insulate and air seal the shaft walls of an existing skylight.

    • Inspect the existing skylight for signs of water leakage; repair flashing and replace damaged framing as necessary.
    • Choose an air barrier material - either rigid insulation, drywall, or sprayed polyurethane foam insulation.
    • If the air barrier will be rigid insulation or drywall, remove any existing insulation if insufficient or sagging. Fill the skylight shaft framing cavities with unfaced batt insulation. Caulk framing then cover with rigid insulation or drywall. Tape and seal all joints in the rigid insulation or drywall.
    • If the air barrier will be sprayed polyurethane foam, remove any existing insulation and fill the cavities with either open- or closed-cell spray foam.
    • Follow the steps in the Description tab.

    For more information on conditions that may be encountered when working with walls in existing homes, see the assessment guide on attics.

    See the U.S. Department of Energy’s Standard Work Specifications. for more on air sealing and insulation skylights and follow safe work practices as described. 

    DESCRIPTION

    Retrofit an existing skylight shaft by adding an air barrier and insulation to the shaft walls. This work will be performed from the attic side of the skylight shaft, typically using rigid insulation or drywall or sprayed polyurethane foam insulation. If the air barrier will be rigid insulation or drywall, the framing cavities should be filled with insulation. Unfaced fiberglass batt insulation is typical, but almost any unfaced cavity insulation may be used as long as it will remain in place with minimal settling. Where sprayed polyurethane foam (SPF) insulation is used as the air barrier, follow the applicable code requirements regarding the use of a thermal or ignition barrier. Sometimes this barrier is a coating that is sprayed directly onto the surface of the SPF. In other cases material such as drywall is used as the thermal barrier to separate the SPF from adjacent construction.

    This work will be performed from inside the attic so use safe work practices and be aware of hazardous conditions as described in the attic assessment guide.

    How to Insulate and Air Seal Skylight Shaft Walls

    1. Inspect the existing skylight for signs of water leakage, such as water stains and rot. Repair skylight flashing (from the roof exterior) and replace any damaged framing as necessary.
    2. Set aside existing attic floor insulation to expose the framing at the base of the skylight shaft to be air sealed.
    3. Determine what material will constitute the air barrier around the shaft wall - typically either rigid insulation, drywall, or sprayed polyurethane foam insulation.
    4. If using rigid foam or drywall as the air barrier:
      • Remove any existing insulation in framing cavities around the skylight shaft if it is insufficient, wet, sagging, or pest infested. If the insulation is unfaced batt in good shape and of sufficient quantity, leave it in place.
      • Install new unfaced batt insulation as needed to completely fill the framing cavities of the skylight shaft.
      • Apply a thick bead of caulk to the face of framing at the top, bottom, and sides on each side of the shaft.
      • Nail or screw the rigid insulation or drywall in place over the caulked framing, as shown in the Description tab. Tape and seal all joints in the rigid insulation or drywall.
    5. If the air barrier to be used is sprayed polyurethane foam (SPF) insulation, remove any old insulation and fill the cavities of the skylight framing with the SPF. Both open- and closed-cell SPF insulations are acceptable in any climate zone for this application.
    6. Replace floor insulation around the base of the skylight shaft.

    COMPLIANCE 

    See Compliance tab. 

    More

    More Info.

    Access to some references may require purchase from the publisher. While we continually update our database, links may have changed since posting. Please contact our webmaster if you find broken links.

    References and Resources*
    Author(s)
    U.S. Environmental Protection Agency
    Organization(s)
    EPA
    Publication Date
    Description
    Guide describing details that serve as a visual reference for each of the line items in the Thermal Enclosure System Rater Checklist.
    Author(s)
    U.S. Environmental Protection Agency
    Organization(s)
    EPA
    Publication Date
    Description
    Information sheet outlining the criteria for ENERGY STAR qualified, windows, doors, and skylights.
    Author(s)
    American Architectural Manufacturers Association,
    Canadian Standards Association,
    CSA Group,
    Window & Door Manufacturers Association
    Organization(s)
    AAMA,
    CSA,
    CSA Group,
    WDMA,
    Fenestration & Glazing Industry Alliance,
    FGIA
    Publication Date
    Description
    2017 version of a standard covering requirements for single- and dual-pane windows, glazed side-hinged door systems, sliding doors, tubular daylighting devices, and unit skylights developed jointly by the American Architectural Manufacturers Association (AAMA), the Canadian Standards Association...
    *For non-dated media, such as websites, the date listed is the date accessed.
    Contributors to this Guide

    The following authors and organizations contributed to the content in this Guide.

    Sales
    Building Science Measures
    Building Science-to-Sales Translator

    Fully Aligned Air Barriers = Whole-House Draft Barrier

    Image(s)
    Technical Description

    A whole-house draft barrier is a continuous layer of air-tight materials that block air leaks. This barrier can be integrated with other materials to also function as a water barrier, thermal barrier, and vapor barrier. For example, rigid foam insulation can be used to block thermal flow as well as air flow when seams are sealed with tape, caulk, adhesives, or liquid-applied sealants. Some rigid foams have an integrated water control layer as well. Additionally, drywall can serve as an interior air barrier when the seams are taped and spackled, and caulk, spray foam, or gaskets are used to seal around wiring, plumbing, and other penetrations. It also serves as the vapor barrier when finished with paint. Insulation should be in full contact with the air barrier layer.

    Whole-House Draft Barrier
    Sales Message

    Whole-house draft barriers block air flow that can undermine the thermal protection with a complete high-performance insulation system. What this means to you is less wasted energy along with enhanced comfort, quiet, and durability. Wouldn’t you agree it would be a shame to only get a partial return on your investment in advanced insulation?

    Last Updated

    Mobile Field Kit

    The Building America Field Kit allows you to save items to your profile for review or use on-site.

    Sign Up  or  Log In

    Did you find this information helpful?

    If you have questions and/or would like a reply to this feedback, please include your e-mail address in the message.
    This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.