Skip to main content

Water Managed Roof – Re-roofing and Adding Insulation over a Flat Roof

    Scope
    Scope Images
    Image
    Existing low-slope (“flat”) roof and brick masonry walls with a new fully adhered air barrier membrane plus polyisocyanurate rigid foam insulation and a roofing membrane water control layer
    Scope

    Retrofit an existing flat roof to improve thermal, water, and air control performance as follows:

    • Remove the existing roofing membrane and inspect the roof for any deficiencies.
    • Make the necessary corrections to the roof framing and decking prior to beginning the new work.
    • Air seal wall cavities made accessible by roof demolition and install insulation in the roof cavity.
    • Provide a continuous air control layer within the roof assembly. Ensure the roof assembly air control layer is connected to the wall (and other roof elements) air control layer.
    • Install polyisocyanurate rigid foam insulation over the air control layer. Ensure that the ratio of rigid foam (“air impermeable insulation”) to cavity insulation (“air permeable insulation” meets the code requirements to avoid condensation.
    • Install insulation cover board and roofing membrane with flashing as the water control layer.
    • Flash around all roof penetrations, including blocking added for PV racks.
    • Slope the roof deck to a drain or scuppers by installing either tapered sleepers below the structural sheathing, or tapered insulation.
    • Address combustion safety and controlled mechanical ventilation as needed, given the increased airtightness associated with this retrofit.

    For more on roof/wall connections, see the U.S. Department of Energy’s Standard Work Specifications.

    See the Compliance Tab for related codes and standards requirements, and criteria to meet national programs such as DOE’s Zero Energy Ready Home programENERGY STAR Single-Family New Homes, and Indoor airPLUS.

    Description
    Description

    Controlling rainwater is the single most important factor in the design and construction of durable roof assemblies. The fundamental principle of water management is to shed water by layering materials in such a way that water is directed downwards and outwards out of the building or away from the building. The key to this fundamental principle is drainage.

    When a flat roof is retrofitted by adding rigid foam insulation above the existing roof sheathing, the new air and water control layers must be carefully integrated with the existing roof structures.

    The assembly shown here is an unvented roof assembly and must meet relevant code requirements (Table R806.4 Insulation for Condensation Control of the 2009 IRC (ICC 2009a) and Table R806.5 Insulation for Condensation Control of the 2012 IRC (2012a). The ratio of air-impermeable insulation (polyisocyanurate) to air-permeable insulation (cavity fill) must be sufficient to avoid condensation problems. Assemblies with greater depth of cavity fill insulation require more rigid board insulation. Per 2012 IRC Section806.5, the interior of the roof (gypsum board or plaster) can have a Class II or Class III vapor retarder; a Class I vapor barrier (polyethylene) is prohibited as it will eliminate drying of the assembly. For further explanation, see IRC FAQ: Conditioned Attics.

    Polyisocyanurate is a suitable rigid foam for installing above the roof deck. The rigid foam can be installed over new sheathing coated with an integrated water-resistive barrier as shown in Figure 1 or the insulation can be installed over the existing roof sheathing, which is first covered with a fully adhered air control membrane that extends up the parapet sides above the flat roof as shown in Figure 2. If foil-faced polyisocyanurate rigid foam insulation is used, a protective layer of insulation cover board should be installed over it prior to installing the roofing membrane water control layer, as shown in Figures 1, 2 and 3. Glass fiber-faced polyisocyanurate can be installed without an insulation cover board.

    “Flat” roofs should never be flat. All low-slope roofs must be sloped to drains (as shown in Figure 4) or scuppers at a minimum slope of ¼ inch per foot (ASTM 2009). It is vital that any roof penetrations (drains, skylights, or mechanical curbs) are properly flashed to prevent water entry. The materials that form the water control layer (in this case the roof membrane) should overlap each other in shingle fashion or be sealed in a watertight manner (in the field of the roof if the slope is insufficient to rely on shingle-lapped water shedding).

    Skylights, mechanical curbs, and other roof penetrations must be integrated into the roof’s drainage plane(roofing membrane) (see Figures 5 and 6). Membranes or formable flashings that line these curbed openings are all elements of the roof water control layer. These approaches work best when they are sloped toward the roof drain, so that rainwater is directed off of the building.

    Existing flat roof and brick masonry walls are retrofitted with polyisocyanurate rigid foam insulation plus new OSB sheathing coated with an integrated water-resistant barrier that serves as an air control layer.
    Figure 1. Existing flat roof and brick masonry walls are retrofitted with polyisocyanurate rigid foam insulation plus new OSB sheathing coated with an integrated water-resistant barrier that serves as an air control layer.

     

    Existing flat roof and brick masonry walls are retrofitted with a new fully adhered air barrier membrane plus polyisocyanurate rigid foam insulation and a roofing membrane water control layer.
    Figure 2. Existing flat roof and brick masonry walls are retrofitted with a new fully adhered air barrier membrane plus polyisocyanurate rigid foam insulation and a roofing membrane water control layer.

     

    Existing flat roof and wood-framed walls are retrofitted with a new fully adhered air barrier membrane plus polyisocyanurate rigid foam insulation and a roofing membrane water control layer.
    Figure 3. Existing flat roof and wood-framed walls are retrofitted with a new fully adhered air barrier membrane plus polyisocyanurate rigid foam insulation and a roofing membrane water control layer.

     

    A roof drain is installed in an existing flat roof retrofitted with above-deck rigid foam insulation that is integrated with new air and water control layers.
    Figure 4. A roof drain is installed in an existing flat roof retrofitted with above-deck rigid foam insulation that is integrated with new air and water control layers.

     

    The mechanical curb for a skylight is integrated with the water management and air control layers on a flat roof retrofitted to include new above-deck rigid foam insulation.
    Figure 5. The mechanical curb for a skylight is integrated with the water management and air control layers on a flat roof retrofitted to include new above-deck rigid foam insulation.

     

    The blocking for a new PV roof-mounting system is integrated with new rigid foam and the air and water control layers installed over an existing flat roof.
    Figure 6. The blocking for a new PV roof-mounting system is integrated with new rigid foam and the air and water control layers installed over an existing flat roof.

     

    How to Re-Roof a Flat Roof

    1. Inspect the structural integrity of the roof. Pooling water (seen in Figure below) is a sign that more slope and drains or scuppers are needed. Remove the existing roof membrane, insulation, and sheathing (where needed) and check the roof framing for any deficiencies, rot, insect damage, etc. (see Figure below). Do not proceed if any repairs need to be performed. Based on the findings, revise the roof assembly and review specific detailing as needed. Follow the minimum requirements of the current adopted building and energy codes.
      The existing flat roof before removal of membrane shows lack of slope allowing water to pool on the surface.
      Figure 7. The existing flat roof before removal of membrane shows lack of slope allowing water to pool on the surface. (Source: Building Science Corporation.)
      Sheathing is removed from a flat roof to retrofit with air sealing, insulation, and water control layers.
      Figure 8. Sheathing is removed from a flat roof to retrofit with air sealing, insulation, and water control layers. (Source: Building Science Corporation.)
    2. Remove two or three roof sheathing boards near the perimeter of the roof, leaving one or two boards at the parapet (Figure below). Mechanically fasten a strip of pressure-treated plywood to the interior vertical face of the parapet to allow for attachment of the strip of fully adhered air barrier membrane. Install a strip of OSB sheathing with an integrated water-resistive barrier at the roof perimeter adjacent to the parapet on top of the remaining board sheathing (Figure below). Provide a continuous bead of sealant between the existing board sheathing and a strip of new roof sheathing.
      The existing sheathing boards are removed near the perimeter of the flat roof and pressure-treated plywood is installed at the vertical face of the parapet.
      Figure 9. The existing sheathing boards are removed near the perimeter of the flat roof and pressure-treated plywood is installed at the vertical face of the parapet. (Source: Building Science Corporation.)
      A strip of OSB sheathing is installed along the perimeter when retrofitting a flat roof with a parapet.
      Figure 10. A strip of OSB sheathing is installed along the perimeter when retrofitting a flat roof with a parapet. (Source: Building Science Corporation.)
    3. Spray 2 inches of closed-cell spray foam in the roof cavity at the wall perimeter to create an air barrier connection between the wall and the roof, and to provide adequate thermal resistance to prevent condensation (Figures below). The area should be free of debris and dust prior to spraying for adequate adhesion. Install fibrous insulation (e.g., cellulose) in the rafter cavities beneath the existing board roof sheathing (Figures below). Re-install the roof sheathing boards.
      Closed-cell foam is sprayed into roof cavities along the masonry parapet wall to form a continuous air barrier between the wall and the sheathing of the flat roof.
      Figure 11. Closed-cell foam is sprayed into roof cavities along the masonry parapet wall to form a continuous air barrier between the wall and the sheathing of the flat roof. (Source: Building Science Corporation.)

      Closed-cell spray foam fills the roof joist cavities forming an air barrier between the masonry parapet wall and the roof sheathing.
      Figure 12. Closed-cell spray foam fills the roof joist cavities forming an air barrier between the masonry parapet wall and the roof sheathing. (Source: Building Science Corporation.)
       
      The base of the plywood parapet is air sealed with spray foam and fibrous insulation is installed in the rafter cavities in this flat roof retrofit.
      Figure 13. The base of the plywood parapet is air sealed with spray foam and fibrous insulation is installed in the rafter cavities in this flat roof retrofit. (Source: Building Science Corporation.)
       
      Roofing paper protects the top of the new plywood parapet while the base of the parapet is air sealed with spray foam and fibrous insulation is installed in the rafter cavities in this flat roof retrofit.
      Figure 14. Roofing paper protects the top of the new plywood parapet while the base of the parapet is air sealed with spray foam and fibrous insulation is installed in the rafter cavities in this flat roof retrofit. (Source: Building Science Corporation.)
    4. If needed to create a slope, install sleepers (tapered wood furring strips) on the roof rafters prior to installing the new roof sheathing (Figure below). Install OSB sheathing with an integrated water-resistive barrier over the entire field of the roof (Figure below). Seal all of the sheathing seams with appropriate tape that is applied to a clean surface and pressed on with a roller to ensure good adhesion. This coated, taped OSB is the air control layer at the field of the roof. Install a strip of fully adhered air barrier membrane on top of the new roof sheathing at the roof perimeter adjacent to the parapet and extend it to the top of plywood to form an air barrier connection to the parapet wall. Seal all penetrations, such as drains, skylights, and mechanical curbs, in an airtight and durable manner to the air control layer.
      ALTERNATELY, instead of the coated OSB, install a fully adhered air barrier membrane over the existing roof sheathing and extend up to the top of the plywood at the parapet to form a continuous air control layer. Seal all penetrations, such as drains, skylights, and mechanical curbs, in an airtight and durable manner.
      Sleepers (tapered wood furring strips) are installed over the existing board sheathing to slope the new sheathing toward the drain in this flat roof retrofit.
      Figure 15. Sleepers (tapered wood furring strips) are installed over the existing board sheathing to slope the new sheathing toward the drain in this flat roof retrofit. (Source: Building Science Corporation.)
      New coated OSB roof sheathing is installed over the existing sheathing of the flat roof and taped at the seams to provide a continuous air barrier.
      Figure 16. New coated OSB roof sheathing is installed over the existing sheathing of the flat roof and taped at the seams to provide a continuous air barrier. (Source: Building Science Corporation.)
    5. Install polyisocyanurate rigid foam insulation over the roof sheathing (Figure below). The ratio of air-impermeable insulation (polyisocyanurate) to air-permeable insulation (cavity fill) must be sufficient to avoid condensation problems, per Section R806.4 of the 2009 IRC (ICC 2009a) and Section R806 of the 2012 IRC (2012a). If tapered sleepers are not installed, provide tapered insulation to ensure the roof is sloped to drain. Fit the joints of the insulation together tightly. When installing multiple layers, offset the seams in two directions, add a continuous bead of sealant at the perimeter of the roof between each layer, and tape the seams of each layer. Install wood blocking for future photovoltaic (PV) panel installation (Figure below). The surface of the blocking must stand proud of the roof deck to reduce water penetration risks at fastener penetrations (Figure below). Install insulation cover board (typically fiberglass-faced gypsum board) over the polyisocyanurate rigid foam insulation. Ensure compatibility of the cover board with the roof assembly.
      Polyisocyanurate rigid foam insulation is installed in multiple layers with staggered, taped seams over the flat roof. Note the continuous bead of sealant at the roof perimeter between each layer.
      Figure 17. Polyisocyanurate rigid foam insulation is installed in multiple layers with staggered, taped seams over the flat roof. Note the continuous bead of sealant at the roof perimeter between each layer. (Source: Building Science Corporation.)
       
      Wood blocking for future PV panel installation is installed in the layers of polyisocyanurate rigid foam insulation during a flat roof retrofit.
      Figure 18. Wood blocking for future PV panel installation is installed in the layers of polyisocyanurate rigid foam insulation during a flat roof retrofit. (Source: Building Science Corporation.)
       
      The wood blocking for future PV panel installation extends above the surface of the top layer of polyisocyanurate rigid foam insulation installed as part of a flat roof retrofit.
      Figure 19. The wood blocking for future PV panel installation extends above the surface of the top layer of polyisocyanurate rigid foam insulation installed as part of a flat roof retrofit. (Source: Building Science Corporation.)
    6. Install roofing membrane over the insulation cover board and lap it over the parapet to provide a continuous water control layer (Figure 20). Seal all penetrations, such as drains, skylights, mechanical curbs, and PV blocking against water leaks per new construction best practices (Figures 21, 22, and 23). Install metal cap flashing at the parapet over the roofing membrane. Provide drip edges on either side of the cap flashing to prevent staining of the building façade. (See Figure below and BSI-050: Parapets—Where Roofs Meet Walls.)
      Roofing membrane is installed over polyisocyanurate rigid foam insulation and insulation cover board that has been cut to fit around locations for blocking for the PV system rack.
      Figure 20. Roofing membrane is installed over polyisocyanurate rigid foam insulation and insulation cover board that has been cut to fit around locations for blocking for the PV system rack. (Source: Building Science Corporation.)

      Blocking installed on a flat roof for a PV system rack is sealed around the edges with sealant then will be covered with self-adhering roof membrane to prevent water leakage.
      Figure 21. Blocking installed on a flat roof for a PV system rack is sealed around the edges with sealant then will be covered with self-adhering roof membrane to prevent water leakage. (Source: Building Science Corporation.)

      The blocking is completely flashed with roofing membrane before the PV rack hardware is attached on a flat roof.
      Figure 22. The blocking is completely flashed with roofing membrane before the PV rack hardware is attached on a flat roof. (Source: Building Science Corporation.)
       
      Strips of roofing membrane are used to flash around a skylight on a flat roof retrofit.
      Figure 23. Strips of roofing membrane are used to flash around a skylight on a flat roof retrofit. (Source: Building Science Corporation.)
       
      Metal cap flashing is installed over the roof parapet and extends down over the roofing membrane (which extends up the sides of the parapet wall).
      Figure 24. Metal cap flashing is installed over the roof parapet and extends down over the roofing membrane (which extends up the sides of the parapet wall). A drip edge on each side of the flashing directs water to drip away from the walls, to minimize the likelihood of staining. (Source: Building Science Corporation.)
    7. Install walking mats to protect the membrane surface when accessing the flat roof (Figure below).
      The retrofitted flat roof has PV panels and walking mats installed over the roofing membrane.
      Figure 25. The retrofitted flat roof has PV panels and walking mats installed over the roofing membrane. (Source: Building Science Corporation.)
    Success
    Ensuring Success

    Provide the water control layer in the roof assembly and install it in a continuous manner. Ensure it is connected to the water control layer of the adjacent assemblies and roof elements, such as skylights, mechanical curbs, and drains.

    Provide the air control layer in the roof assembly and install it in a continuous manner. Ensure it is connected to the air control layer of the adjacent assemblies and roof elements, such as skylights, mechanical curbs, and drains.

    Slope the roof deck to a drain or scupper (with a minimum slope of .25 inch per foot).

    The ratio of air-impermeable insulation (polyisocyanurate) to air-permeable insulation (cavity fill) must be sufficient to avoid condensation problems, per Section R806.4 of the 2009 IRC (ICC 2009a) and Section R806 of the 2012 IRC (2012a).

    Remediate any hazardous conditions that will be affected (e.g., exposed or aggravated) by the planned work. Examples of hazardous materials that may be found in roof assemblies of existing structures include (but are not limited to) lead, asbestos, mold, animal dropping/remains, etc. Follow applicable laws and industry procedures for mitigation of hazardous materials. Engage the services of a qualified professional when needed.

    Provide minimum combustion safety by providing direct-vent sealed-combustion equipment or forced draft equipment (see Direct Vent Equipment). When furnaces, boilers, and water heaters are installed within the home’s pressure boundary, ideally this equipment would be direct-vent sealed-combustion equipment. If existing equipment is not direct-vent sealed-combustion or forced draft, the homeowners must decide whether to

    • replace equipment with direct vent or forced draft equipment, or
    • retrofit forced-draft to existing equipment.

    Provide whole-house and local exhaust (source control) mechanical ventilation complying with Section M1507 of the 2012 International Residential Code. Mechanical ventilation may be installed as part of the larger attic/roof retrofit project.

    Climate
    Climate

    The roof assembly should be designed for a specific hygrothermal region, rain exposure zone, and interior climate.

    The map in Figure 1 shows the climate zones for states that have adopted energy codes equivalent to the International Energy Conservation Code (IECC) 2009, 12, 15, and 18. The map in Figure 2 shows the climate zones for states that have adopted energy codes equivalent to the IECC 2021. Climate zone-specific requirements specified in the IECC are shown in the Compliance Tab of this guide. 

    Climate Zone Map from IECC 2009, 12, 15, and 18.

    Figure 1. Climate Zone Map from IECC 2009, 12, 15, and 18. (Source: 2012 IECC)

     

    Climate Zone Map from IECC 2021.

    Figure 2. Climate Zone Map from IECC 2021. (Source: 2021 IECC)

     

    The insulation levels should be based on the minimum requirements for vapor control in the current adopted building code and the minimum requirements for thermal control in the current energy code. Table 1 provides the minimum thermal resistance (R-value) requirements specified in the 2009 IECC (ICC 2009b) and the 2012 IECC (ICC 2012b) based on climate zone for roof assemblies.

    Attic Insulation Requirements per the 2009 and 2012 IECC.

    Table 1. Attic Insulation Requirements in the 2009 and 2012 IECC. (Source: 2009 IECC and 2012 IECC)

     

    It is important to maintain a sufficient ratio of exterior insulation to total roof assembly insulation. In colder climate zones, the amount of exterior (rigid) insulation needed to avoid condensation problems increases. Table 2 provides information on minimum levels of air impermeable insulation for condensation control specified in Table R806.4 Insulation for Condensation Control of the 2009 IRC (ICC 2009a) and Table R806.5 Insulation for Condensation Control of the 2012 IRC (2012a).

    Insulation required for Condensation Control per the 2009 and 2012 IRC.

    Table 2. Insulation required for Condensation Control in the 2009 and 2012 IRC. (Source: 2009 IRC and 2012 IRC)

     

    Training
    Right and Wrong Images
    Image
    Right – A fully adhered roof membrane provides thorough water and wind protection in this mountain top location.
    Right – A fully adhered roof membrane provides thorough water and wind protection in this mountain top location.
    Image
    Weather resistant barrier is wrapped over the edge from roof to wall sheathing to provide a continuous air barrier at this transition.
    Weather resistant barrier is wrapped over the edge from roof to wall sheathing to provide a continuous air barrier at this transition.
    Image
    Right - This shed roof is constructed with 1X4 furring strips installed over the decking and underlayment for ventilation beneath the metal roofing.
    Right - This shed roof is constructed with 1X4 furring strips installed over the decking and underlayment for ventilation beneath the metal roofing.
    Image
    Right - A lattice of 1X4 furring strips provides a ventilation gap between the decking and metal roofing for this shed roof.
    Right - A lattice of 1X4 furring strips provides a ventilation gap between the decking and metal roofing for this shed roof.
    Compliance

    Compliance

    The Compliance tab contains both program and code information. Code language is excerpted and summarized below. For exact code language, refer to the applicable code, which may require purchase from the publisher. While we continually update our database, links may have changed since posting. Please contact our webmaster if you find broken links.

     

    ENERGY STAR Single-Family New Homes, Version 3/3.1 (Rev. 11)

    National Water Management System Builder Requirements

    3. Water-Managed Roof Assembly.
    3.1 Step and kick-out flashing at all roof-wall intersections, extending ≥ 4” on wall surface above roof deck and integrated shingle-style with drainage plane above; boot / collar flashing at all roof penetrations.13
    3.2 For homes that don’t have a slab-on-grade foundation and do have expansive or collapsible soils, gutters & downspouts provided that empty to lateral piping that discharges water on sloping final grade ≥ 5 ft. from foundation, or to underground catchment system not connected to the foundation drain system that discharges water ≥ 10 ft. from foundation. Alternatives & exemptions in Footnote.4, 14, 15
    3.3 Self-adhering polymer-modified bituminous membrane at all valleys & roof deck penetrations.4, 16
    3.4 In 2009 IECC Climate Zones 5 & higher, self-adhering polymer-modified bituminous membrane over sheathing at eaves from the edge of the roof line to > 2 ft. up roof deck from the interior plane of the exterior wall.4, 16

    Footnote 4) Not required in Dry (B) climates as shown in 2009 IECC Figure 301.1 and Table 301.1.

    Footnote 13) Intersecting wall siding shall terminate 1 in. above the roof or higher, per manufacturer's recommendations. Continuous flashing shall be installed in place of step flashing for metal and rubber membrane roofs.

    Footnote 14) The assessment of whether the soil is expansive or collapsible shall be completed by a certified hydrologist, soil scientist, or engineer.

    Footnote 15) Any of the following are permitted to be used as alternatives to Item 3.2: a) a roof design that deposits rainwater to a grade-level rock bed with a waterproof liner and a lateral drain pipe that meets discharge requirements per Item 3.2; b) a rainwater harvesting system that drains overflow to meet discharge requirements per Item 3.2; or c) a continuous rubber membrane (e.g. EPDM) that is aligned with the foundation wall from final grade to ≥ 8 in. below grade and then slopes ≥ 0.5 in. per ft. away from the home for at least 5 ft., with Group I Soils (as defined in Footnote 9) covering the membrane to within 3 in. of final grade.

    Footnote 16) As an alternative, any applicable option in 2009 IRC Section R905.2.8.2 is permitted to be used to meet Item 3.3 and any option in 2009 IRC Section R905.2.7.1 is permitted to be used to meet Item 3.4. EPA recommends, but does not require, that products meet ASTM D1970. In addition, any option in 2009 IRC Section R905.13 is permitted to be used to meet either Item 3.3 or 3.4.

    Please see the ENERGY STAR Single-Family New Homes Implementation Timeline for the program version and revision currently applicable in your state.

     

    DOE Zero Energy Ready Home (Revision 07)

    The DOE Zero Energy Ready Home Program is a voluntary high-performance home labeling program for new homes operated by the U.S. Department of Energy. Builders and remodelers who are performing retrofits on existing homes are welcome to seek certification for those homes through this voluntary program.

    Exhibit 1 Mandatory Requirements.
    Exhibit 1, Item 1) Certified under the ENERGY STAR Qualified Homes Program or the ENERGY STAR Multifamily New Construction Program.
    Exhibit 2, Item 2) Ceiling, wall, floor, and slab insulation shall meet or exceed 2015 IECC levels and achieve Grade 1 installation, per RESNET standards.

     

    2009-2021 IECC and IRC Insulation Requirements Table

    The minimum insulation requirements for ceilings, walls, floors, and foundations in new homes, as listed in the 2009, 2012, 2015, 2018, and 2021 IECC and IRC, can be found in this table

     

    2009, 2012, 20152018, and 2021 International Residential Code (IRC)

    Section R801.3 Roof drainage.

    Section R907 (R908 in 2015, 2018, and 2021 IRC) Reroofing.

    Section R901 Roof Assemblies. This section outlines the design, materials, construction, and quality of roof assemblies.

    Retrofit:  2009, 2012, 2015, 2018,  and 2021 IRC

    Section R102.7.1 Additions, alterations, or repairs. Additions, alterations, renovations, or repairs shall conform to the provisions of this code, without requiring the unaltered portions of the existing building to comply with the requirements of this code, unless otherwise stated. (See code for additional requirements and exceptions.)

    Appendix J regulates the repair, renovation, alteration, and reconstruction of existing buildings and is intended to encourage their continued safe use.

    More

    More Info.

    Access to some references may require purchase from the publisher. While we continually update our database, links may have changed since posting. Please contact our webmaster if you find broken links.

    Case Studies
    Author(s)
    Pacific Northwest National Laboratory,
    U.S. Department of Energy
    Organization(s)
    PNNL,
    USDOE
    Publication Date
    Description
    Case study describing a DOE Zero Energy Ready Home 2013 Housing Innovation Award Winner in Seattle, WA, that scored HERS 34 without PV.
    References and Resources*
    Author(s)
    Neuhauser Ken,
    Gates Cathy,
    Pettit Betsy
    Organization(s)
    Building Science Corporation,
    BSC
    Publication Date
    Description
    Guidebook providing useful examples of high performance retrofit techniques for the building enclosure of wood frame residential construction in a cold and somewhat wet climate.
    Author(s)
    National Roofing Contractors Association
    Organization(s)
    National Roofing Contractors Association
    Publication Date
    Description
    Manuals describing design, materials, and installation techniques applicable to almost all types of roof systems; four-volume set includes Metal Panel and SPF Roof Systems, Membrane Roof Systems, Architectural Metal Flashing and Condensation and Air Leakage Control, and Steep-Slope Roof Systems.
    Author(s)
    Lstiburek Joseph W
    Organization(s)
    Building Science Corporation,
    BSC
    Publication Date
    Description
    Book presenting the best techniques for energy and resource efficient residential construction in the colder climates of North America.
    *For non-dated media, such as websites, the date listed is the date accessed.
    Contributors to this Guide

    The following authors and organizations contributed to the content in this Guide.

    Building Science Corporation, lead for the Building Science Consortium (BSC), a DOE Building America Research Team

    Last Updated

    Did you find this information helpful?

    If you have questions and/or would like a reply to this feedback, please include your e-mail address in the message.
    This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.