Skip to main content

Exterior Insulation for Existing Foundation Walls

    Scope
    Scope Images
    Image
    Rigid insulation is installed on the exterior side of the flat foundation wall
    Scope

    Insulate a new foundation wall or an existing foundation wall by adding rigid insulation to the exterior side as follows:

    • Locate underground utilities.
    • Excavate the foundation perimeter.
    • Install a footing perimeter drain pipe to provide adequate exterior drainage.
    • Install damp proofing or a waterproofing membrane on the exterior side of the foundation wall and footing
    • Install rigid board insulation (such as XPS, foil-faced polyisocyanurate, or rigid mineral fiber) on the exterior wall from the top of the footing to the bottom of the cladding to at least the minimum R-value specified in the local building code.
    • Install an aluminum coil stock or sheet metal protective cover for the rigid insulating sheathing.
    • Back-fill excavation to within 8 inches of the finished grade with free-draining backfill.
    • Install closed-cell sprayed polyurethane foam (SPF) insulation on the interior side of the rim joist.

    Note that this assembly is appropriate only for flat foundation walls. Due to the cost and logistical difficulties, this measure is typically more suitable for new construction rather than a retrofit project.

    See the Compliance Tab for links to related codes and standards and voluntary federal energy-efficiency program requirements.

    Description
    Description

    Rigid board insulation (such as XPS, foil-faced polyisocyanurate, or rigid mineral fiber) can be installed on the exterior side of homes with smooth foundation walls such as those made of cast concrete or concrete block. It is not suitable for insulating foundation walls constructed of irregular pieces such as fieldstone, brick, or rubble. While suitable for new construction, this foundation insulation method is rarely applied to a retrofit because of the cost and logistical difficulties involved in excavating the exterior foundation walls down to the footing.

    The rim joist can be insulated on the interior with sprayed polyurethane foam (SPF) insulation applied from inside the basement or crawlspace. The spray foam should cover the sill plate and extend from the top of the foundation wall to the underside of the subfloor to provide continuity of the thermal control layer at the transition between the rigid insulation below grade and the cavity insulation above grade.

    In retrofit cases, an assessment should be made of the condition of the sill prior to beginning the retrofit. If there is no capillary break under the sill and/or if the sill is within 12 inches of the ground, it is possible that it has suffered water damage. If so, the damaged pieces should be replaced and at the same time, a capillary break should be installed under the new pieces. If there is no capillary break under the sill and /or the sill is within 12 inches of the ground but there is no indication of damage, then it is likely that the sill has been able to dry. Depending on the properties of the exterior rigid insulation and waterproofing, the new assembly may have limited drying potential to the exterior, and if so, care must be taken to preserve the drying potential of the assembly to the interior.

    Even though foundation wall materials are water tolerant, measures should be taken to protect the walls from bulk water and a number of strategies can be implemented to this end (see Figure 1). If the grade around the perimeter does not slope away from the house, for example, grading adjustments should be made so that it slopes away at 5% grade for at least the first 3 feet and if possible, 10 feet. If gutters are installed, the downspouts should direct water away from the perimeter of the house and the gutter system must be regularly maintained to prevent overflowing, leaks, or breaks in the system as these can concentrate water at the building’s foundation. A trench of gravel around the perimeter that extends out at least as far as the roof drip edge may also be provided to further mitigate bulk water problems. The gravel trench helps disperse bulk water that comes from the roof so that the top of the foundation wall is not continually splashed. These ground water control strategies should be implemented at the discretion of the practitioner based on project goals and site conditions.

    The foundation walls themselves should also be protected from water with damp-proofing or a waterproofing membrane (at the discretion of the practitioner) applied directly to the concrete before installing the rigid foam. A drainage mat of high-density polyethylene dimple mat should be installed over the rigid foam, unless the insulation itself is free draining. The damp-proofing or the waterproofing membrane should be integrated to the water control layer of the sheathing above with a transition strip of self-adhered membrane. This membrane also provides termite protection.

    A protective cover of aluminum coil stock or sheet metal should be installed over the top portion of the rigid insulation to provide damage protection and serve as a closure piece. The top edge of this flashing should extend up under the rigid foam sheathing or house wrap and under the cladding. A strip of self-adhered membrane should cover the top edge of this flashing.

    Rigid insulation and water control layers are installed on the exterior of a flat foundation wall; spray foam insulates the rim joist.
    Figure 1. Rigid insulation and water control layers are installed on the exterior of a flat foundation wall; spray foam insulates the rim joist. (Source: Building Science Corporation.)

     

    How to Install Rigid Board Insulation at Exterior of the Foundation Wall

    1. Evaluate the existing foundation wall’s structural integrity and ability to tolerate excavation from grade to footing.
      NOTE: Rubble wall foundations typically are relatively flush and planar to the interior but highly variable and non-planar on the exterior. For rubble wall foundations, proceed with great care when excavating and/or conduct a small-scale excavation test to assess the rubble wall’s exterior.
    2. Locate underground utilities serving the building or passing near the foundation. Implement measures to ensure the protection of these throughout the project. STOP! Do not proceed if underground utilities are not located.
    3. Excavate the foundation perimeter down to the footing and 4 feet out from the foundation wall to provide room to work and to accommodate free-draining back-fill material.
    4. Install a perforated perimeter drain pipe at the footing if none exists. Place the pipe in coarse gravel bed with no fines with filter fabric wrapping around the gravel bed. Slope the drain pipe to a storm water collection system or to a daylight outlet.
    5. Install damp-proofing or a waterproofing membrane per manufacturer’s recommendations (refer to ENERGY STAR Water Management System Builder Checklist Section 1.5 cited above) extending from grade to the base of the foundation wall and over the top of the footing. Note that primer may be required.
    6. Provide a transition strip of fully adhered membrane between the wall sheathing and the foundation wall damp-proofing or a waterproofing membrane as a termite protection and to provide continuity of the water control layers above and below grade.
    7. Install rigid insulation such as XPS, foil-faced polyisocyanurate, or semi-rigid mineral fiber insulation board applied to the outside of the foundation wall. Typically the boards are sufficiently rigid and the spans are small enough to permit the insulation to be loose laid at installation and then held in place by the backfill. The use of adhesives, tape, or temporary supports may be required to hold the insulation in place prior to backfill.
    8. Install an aluminum coil stock or sheet metal protective cover over the top of the rigid foam; extend it up the wall approximately 4 inches with the top edge extending behind the house wrap or rigid foam drainage plane of the above grade wall. The flashing should extend down over the front face of the rigid foam to approximately 6 inches below grade.
    9. Install a fully adhered bituminous membrane across the top edge of the metal flashing protective cover to complete the termite protection.
    10. When work is complete, back-fill the excavation to within no more than 8 inches of the finished grade with free-draining material. Separate the free-draining material from the top soil with filter fabric. Provide a minimum 5% grade slope away from the foundation wall.
    11. From the interior, apply 3 inches of closed-cell spray foam insulation to the interior side of the rim joist extending from the top of the foundation wall to the underside of the subfloor. Concrete block or brick foundation walls will require an interior air control layer such as a parge coat applied over the interior face of the wall with a continuous transition to the spray foam at the top of the wall.
    Success
    Ensuring Success

    Locate the underground gas and electric utilities in the vicinity of the excavation.

    Provide a fully adhered membrane extending from the existing sheathing down onto the foundation wall to protect the wood framing from termites.

    Provide flashing across the top of the exterior insulation and seal it at the top with the membrane to protect the insulation from UV rays and physical damage.

    Install a 4-inch perforated perimeter drain pipe in a gravel bed wrapped in filter fabric to allow for proper drainage.

    Climate
    Climate

    The basement wall assembly should be designed for the specific hygrothermal region, rain exposure zone, and interior climate. The climate zones are shown on the map below, which is taken from Figure C301.1 of the 2012 IECC.

    The map in Figure 1 shows the climate zones for states that have adopted energy codes equivalent to the International Energy Conservation Code (IECC) 2009, 12, 15, and 18. The map in Figure 2 shows the climate zones for states that have adopted energy codes equivalent to the IECC 2021. Climate zone-specific requirements specified in the IECC are shown in the Compliance Tab of this guide. 

    Climate Zone Map from IECC 2009, 12, 15, and 18.

    Figure 1. Climate Zone Map from IECC 2009, 12, 15, and 18. (Source: 2012 IECC)

     

    Climate Zone Map from IECC 2021.

    Figure 2. Climate Zone Map from IECC 2021. (Source: 2021 IECC)

     

    The insulation levels should be based on the minimum requirements for vapor control in the current adopted building code and the minimum requirements for thermal control in the current energy code.  The minimum insulation requirements for ceilings, walls, floors, and foundations in new homes, as listed in the 2009, 2012, 2015, 2018, and 2021 IECC and IRC, can be found in this table

    Termites

    Consult local building code for practices related to termite resistance.

    Training
    Right and Wrong Images
    Image
    Right – Housewrap was properly shingled and taped on this wall assembly which places the housewrap beneath the rigid foam sheathing; wall cavities will be filled with spray foam.
    Right – Housewrap was properly shingled and taped on this wall assembly which places the housewrap beneath the rigid foam sheathing; wall cavities will be filled with spray foam.
    Image
    Right – A dimpled-plastic rain mat was attached to the exterior below-ground walls to help minimize frost damage in cold climates.
    Right – A dimpled-plastic rain mat was attached to the exterior below-ground walls to help minimize frost damage in cold climates.
    Image
    Right – ICFs provide an insulated form for the concrete of the foundation wall.
    Right – ICFs provide an insulated form for the concrete of the foundation wall.
    Image
    Right – Rigid foam is attached to the exterior of this foundation wall.
    Right – Rigid foam is attached to the exterior of this foundation wall.
    Image
    Right – This wall is constructed with the sill plate overhanging the top of the foundation wall so that when rigid foam is installed on the exterior of the foundation wall, its surface will align with the surface of the wall sheathing.
    Right – This wall is constructed with the sill plate overhanging the top of the foundation wall so that when rigid foam is installed on the exterior of the foundation wall, its surface will align with the surface of the wall sheathing.
    Image
    Right – Rigid foam completely covers the foundation walls of the home.
    Right – Rigid foam completely covers the foundation walls of the home.
    Image
    Right – R-20 of XPS and polyiso rigid foam were added on the slab shelf that is part of this precast foundation wall system.
    Right – R-20 of XPS and polyiso rigid foam were added on the slab shelf that is part of this precast foundation wall system.
    Image
    Larsen trusses made of 9-inch I joists, set perpendicular to the exterior wall at 16 inches on center, provide a second wall cavity that can be filled with blown insulation, greatly increasing the insulation value in the walls.
    Larsen trusses made of 9-inch I joists, set perpendicular to the exterior wall at 16 inches on center, provide a second wall cavity that can be filled with blown insulation, greatly increasing the insulation value in the walls.
    Image
    Insulation was added to the walls and ceiling of this existing home from the inside as part of an extensive retrofit to avoid replacing original 1-inch shiplapped sheathing.
    Insulation was added to the walls and ceiling of this existing home from the inside as part of an extensive retrofit to avoid replacing original 1-inch shiplapped sheathing.
    Image
    Right - Rigid foam is installed over a waterproofing membrane that has been applied to the basement foundation walls.
    Right - Rigid foam is installed over a waterproofing membrane that has been applied to the basement foundation walls.
    Image
    Right – This builder installs 1 inch of XPS rigid foam on the exterior of the 2x6 walls then covers the foam with ½-inch plywood sheathing, which serves as a nailing surface for siding and trim.
    Right – This builder installs 1 inch of XPS rigid foam on the exterior of the 2x6 walls then covers the foam with ½-inch plywood sheathing, which serves as a nailing surface for siding and trim.
    Image
    Right – A 1-inch layer of XPS rigid foam covers the 2x6 wall studs and is topped by ½-inch-thick plywood sheathing, which is covered with draining house wrap and serves as a nailing surface for siding and trim.
    Right – A 1-inch layer of XPS rigid foam covers the 2x6 wall studs and is topped by ½-inch-thick plywood sheathing, which is covered with draining house wrap and serves as a nailing surface for siding and trim.
    Presentations
    Videos
    Compliance
    More

    More Info.

    Access to some references may require purchase from the publisher. While we continually update our database, links may have changed since posting. Please contact our webmaster if you find broken links.

    References and Resources*
    Author(s)
    Neuhauser Ken,
    Gates Cathy,
    Pettit Betsy
    Organization(s)
    Building Science Corporation,
    BSC
    Publication Date
    Description
    Guidebook providing useful examples of high performance retrofit techniques for the building enclosure of wood frame residential construction in a cold and somewhat wet climate.
    Author(s)
    U.S. Environmental Protection Agency
    Organization(s)
    EPA
    Publication Date
    Description
    Indoor airPLUS is a voluntary partnership and labeling program that helps new home builders improve the quality of indoor air by requiring construction practices and product specifications that minimize exposure to airborne pollutants and contaminants.
    Author(s)
    U.S. Department of Energy
    Organization(s)
    DOE
    Publication Date
    Description
    Website listing implementation timelines and links to various versions of the DOE Zero Energy Ready Home national program requirements.
    Author(s)
    Burkett Lena,
    Gunderson Patti
    Organization(s)
    U.S. Department of Energy,
    DOE
    Publication Date
    Description
    Fact sheet describing the Extended Plate Wall (EPW) a system that incorporates a 2-inch layer of foam plastic insulative sheathing within the framing for top and bottom plates, streamlining air sealing, window and door installation, weather resistive barrier application, and cladding attachment for...
    Author(s)
    Kochkin Vladimir,
    Shah Nay B
    Organization(s)
    Home Innovation Research Labs,
    HIRL,
    U.S. Department of Energy,
    DOE
    Publication Date
    Description
    The next generation of building enclosures is a key step toward achieving high-performance goals through decreasing energy load demand and enabling advanced space-conditioning systems. Yet the adoption of high-R enclosures and particularly high-R walls has been a slow-growing trend because...
    *For non-dated media, such as websites, the date listed is the date accessed.
    Contributors to this Guide

    The following authors and organizations contributed to the content in this Guide.

    Building Science Corporation, lead for the Building Science Consortium (BSC), a DOE Building America Research Team

    Sales
    Building Science Measures
    Building Science-to-Sales Translator

    High-R Foundation Insulation = High-Efficiency or Ultra-Efficient Foundation Insulation

    Image(s)
    Technical Description

    There are two levels of foundation insulation: high-efficiency insulation, which meets the 2015 International Energy Conservation Code, and ultra-efficient insulation, which is 25% more efficient than this national code. Using high-efficiency and ultra-efficient insulation, along with professional installation (e.g., no gaps, voids, compression, or misalignment with air barriers; complete air barriers; and minimal thermal bridging) creates conditioned spaces that require very little heating and cooling, along with, even comfort and quiet throughout the house.

    High-Efficiency or Ultra-Efficient Foundation Insulation
    Sales Message

    High-efficiency foundation insulation helps provide added thermal protection. What this means to you is less wasted energy along with enhanced comfort and quiet. Knowing there is one opportunity to optimize performance during construction, wouldn’t you agree it’s a great opportunity to meet or exceed future codes?

    Last Updated

    Did you find this information helpful?

    If you have questions and/or would like a reply to this feedback, please include your e-mail address in the message.
    This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.