U.S. Department of Energy U.S. Department of Energy Energy Efficiency and Renewable Energy

Sheetrock to Top Plate

Please Register or Login to Provide Feedback.

Scope


Air Sealing

 

Drywall sealed to top plate at all attic/wall interfaces using caulk, foam, drywall adhesive (but not other construction adhesives), or equivalent material. Either apply sealant directly between drywall and top plate or to the seam between the two from the attic above.

Before insulating the attic, seal all top plate to interior cladding connections with latex foam or caulk to stop air leakage between conditioned and unconditioned space.

        OR

Before installing drywall, use spray foam sealant or gasket product on top plate to air seal once drywall is installed. If this method is used, make sure foam/gasket remains intact during drywall installation.



Description


In simplest terms, a wall is a six-sided box consisting of a horizontal top plate, a horizontal bottom plate, and vertical side studs, with a gypsum board and wall sheathing back, all fastened together to create a wall cavity that is typically filled with insulation when this wall is part of the building’s exterior shell. If air is allowed to flow through the wall cavity, i.e., if the wall cavity is not air tight, the flowing air can reduce the insulation’s effectiveness. If the wall cavity is not airtight, convective loops can also develop within wall cavities, due to temperature differences between the inside and outside surfaces and top and bottom sections of the wall. These convective loops can encourage more air flow, further reducing insulation effectiveness and potentially resulting in moisture problems.

 

To ensure the optimum energy performance and moisture management of the whole house, all of the wall components should be connected to the each other and to the ceiling and floor in a way that creates a continuous and complete air barrier system.

 

Gypsum board drywall is an air barrier material (BSC 2009). The taping of drywall seams results in a plane of airtightness at the field of the wall. However, several steps must be taken
to use this material properly to create a continuous and complete air barrier system. To do this, it is important to create air barrier continuity at the perimeter of drywall assemblies as well as at all penetrations through the drywall. Air barrier continuity at the perimeter of drywall assemblies is achieved by sealing the edges of the drywall to solid framing materials. This requires a continuous bead of sealant along:

  • all exterior wall bottom and top plates,
  • all top plates at insulated ceilings,
  • rough opening perimeters,  
  • both sides of the first interior stud of partition walls (BSC 2009).

 

This air sealing can be achieved by applying caulk, glue, or strips of foam gasket material to the surface of the top plates, bottom plates, and framing around doors and windows before installing the drywall. This would typically be done by the drywall installer. This task should be included in the contract for the appropriate trade depending on the workflow at the specific job site.

 

 

How to Air Seal the Sheetrock to the Top Plate

  1. Apply a continuous bead of caulk or glue or staple a strip of compressible foam gasket material along the top plate along all exterior walls and all interior walls.
  2. Install drywall over caulk, glue, or gasket material. Mud and tape drywall. 

 

 

Install a foam gasket along top plates before installing drywall

Figure 1 - A pliable foam gasket material is stapled along the top plate prior to installing drywall Reference

 

 

 

 

Caulk or glue along top plates before installing drywall

 

Figure 2 - A continuous bead of caulk or glue is applied to the top plates on exterior walls and interior walls that intersect insulated ceilings, as well as rough openings around doors and windows, prior to installing drywall Reference

 

 

 

 

Seal the drywall to the top plates as part of the home’s continuous air barrier

 

Figure 3 - Sealing the drywall to the top plate is one step in forming a continuous, complete air barrier in the home’s exterior shell Reference

 

 



Ensuring Success


When drywall is installed, visually inspect that drywall installer is applying caulk or a foam gasket along surface of top plate before hanging drywall. After drywall installation it may be possible to detect air leakage at this location with an IR camera or smoke pencil during a blower door pressure test. Although taped, mudded drywall should provide some air barrier as well.

 



Climate


No climate specific information applies.



Right and Wrong Images



Presentations

None Available



Videos

None Available




CAD Images

None Available




Compliance


ENERGY STAR Version 3, (Rev. 6)

Thermal Enclosure Checklist, Air Sealing. Cracks in the building envelope fully sealed. Drywall sealed to top plate at all unconditioned attic/wall interfaces using caulk, foam, drywall adhesive (but not other construction adhesives), or equivalent material.  Either apply sealant directly between drywall and top plate or to the seam between the two from the attic above.

DOE Challenge Home

Exhibit 1: Mandatory Requirements. Certified under ENERGY STAR Qualified Homes Version 3

2009 IECC

Table 402.4.2 Air Barrier and Insulation Inspection Component Criteria, Walls: Corners, headers, narrow framing cavities, and rim joists are insulated.* 

 

2009 IRC

Table N1102.4.2 Air Barrier and Insulation Inspection, Walls: Corners, headers, narrow framing cavities, and rim joists are insulated.*

2012 IECC

Table R402.4.1.1 Air Barrier and Insulation Installation, Walls: Junction of foundation and wall sill plates, wall top plate and top of wall, sill plate and rim-band, and rim band and subfloor are sealed. Corners, headers, and rim joists making up the thermal envelope are insulated.*

 

2012 IRC

Table N11402.4.1.1 Air Barrier and Insulation Installation, Walls: Junction of foundation and wall sill plates, wall top plate and top of wall, sill plate and rim-band, and rim band and subfloor are sealed. Corners, headers, and rim joists making up the thermal envelope are insulated.*

 

 

*Due to copyright restrictions, exact code text is not provided.  For specific code text, refer to the applicable code.



Case Studies

None Available


References

  1. 2009 IECC—International Energy Conservation Code

    2009 IECC, International Energy Conservation Code. International Code Council, Washington, D.C.

  2. 2012 IECC—International Energy Conservation Code

    2012 IECC, International Energy Conservation Code.  International Code Council, Washington, D.C.

  3. Air Barriers-Airtight Drywall Approach, Information Sheet 401

    Lstiburek, J. 2009. Air Barriers-Airtight Drywall Approach. Information Sheet 401. Prepared by the Building Science Corporation for the Department of Energy's Building America Program.

  4. DOE Challenge Home National Program Requirements

    DOE. 2012. DOE Challenge Home National Program Requirements (Rev. 02). Office of Energy Efficiency and Renewable Energy, U.S. Department of Energy, Washington, D.C.

  5. ENERGY STAR Qualified Homes, Version 3 (Rev. 06) Inspection Checklist for National Program Requirements

    EPA. 2012. ENERGY STAR Qualified Homes, Version 3 (Rev. 06) Inspection Checklist for National Program Requirements. U.S. Environmental Protection Agency, Washington, D.C.

  6. Thermal Enclosure System Rater Checklist Guidebook

    EPA. 2011. Thermal Enclosure System Rater Checklist Guidebook. U.S. Environmental Protection Agency, Washington, D.C.

  7. Tommy Williams Homes: Zero Energy Home, Longleaf

    Florida Solar Energy Center (FSEC). 2010. Tommy Williams Homes: Zero Energy Home, Longleaf. Prepared by the Florida Solar Energy Center for the U.S. Department of Energy Building America Program.